Rampart featured in Shotcrete Magazine article about the Fort McHenry Tunnel Project

Sep 2, 2014 in Announcements

An article by John Becker in Shotcrete Magazine describes the first phase of the Fort McHenry Tunnel repair project.  The project required 23,000 CF of delaminated concrete repairs in two tunnel bores.  Coastal Gunite Construction chose Rampart to perform the hydrodemolition.  The article featured Rampart’s contributions to the project.  We designed and built custom hydrodemolition robots for use in the bores.  Currently, the third phase of the project is getting underway.  Coastal Gunite has again asked Rampart to team with them on this project.  This final phase will include approximately 81,000 CF of hydrodemolition in all four bores.  To read the entire article, please click here:  http://www.coastalgunite.com/articles/2013Spr_Becker.pdf